• Cost,  Hempcrete

    Hempcrete Downstairs Front Room Install Audit Nov 2016

    Fri 11th (Day 1) Intended : Empty room, remove plaster, coving & picture rail, brush/clean brick walls Achieved : Emptied room, purchased amazon items Sat 12th Intended : nothing Achieved : Removed plaster, cornice & picture rail. Visited Simon & collected Fein multimaster & bahco nail puller. Sun 13th (Day 2) Intended : Trim back floor & ceiling, lift floorboards, clear detritus from underfloor, fix joists in bay window Achieved : Wire brushed & vacuumed brick walls. Trimmed floorboards 100mm back. Major joist repair needed – decided to complete at later stage. Mon 14th Intended : nothing Achieved : Simon visit (2-3hrs). Lifted half of floorboards, removed nails & cleared…